Yantai Port West Port Port Project has completed an investment of approximately 2.1 billion yuan since its construction began. The end of May this year, the project entity invested 13.21 million yuan. among them:
Sunshore Universal Terminal Project: The hydraulic main body completed 34 boxes of prisms, 28 boxes of back filter layers, backfill, 21 cast-in-place caisson roofs, and 3 sections of bottom wall. Auxiliary construction projects are in preparation for tendering.
Large-scale deep-water ore wharf project: The temporary road surface clearing is basically completed, and 50% of the gravel cushion is completed, laying the foundation for the formal construction of the wharf.
Pipeline installation engineering: Pipeline pipelines and docks, vehicle loading and unloading areas, and finished oil tanker pipelines have all been completed; fuel pipelines have been installed 9000 meters, accounting for 65% of the total.
In addition, the first breakwater project, 200,000-ton channel project, Shugang Avenue and street lighting project, production dispatch building project, accident emergency pool, fire water station, and sewage treatment plant have all been completed.
Sunshore Universal Terminal Project: The hydraulic main body completed 34 boxes of prisms, 28 boxes of back filter layers, backfill, 21 cast-in-place caisson roofs, and 3 sections of bottom wall. Auxiliary construction projects are in preparation for tendering.
Large-scale deep-water ore wharf project: The temporary road surface clearing is basically completed, and 50% of the gravel cushion is completed, laying the foundation for the formal construction of the wharf.
Pipeline installation engineering: Pipeline pipelines and docks, vehicle loading and unloading areas, and finished oil tanker pipelines have all been completed; fuel pipelines have been installed 9000 meters, accounting for 65% of the total.
In addition, the first breakwater project, 200,000-ton channel project, Shugang Avenue and street lighting project, production dispatch building project, accident emergency pool, fire water station, and sewage treatment plant have all been completed.